The SDLC pipeline

Delivery plan

Epics laid into sprints, milestones, dependencies and the team, the proposal's schedule.

8 min read7 sections

The Delivery Plan step works out how the project gets delivered: the design's components laid out as epics across sprints, the milestones the client will see, the dependencies between them, and the team the dates assume. The agent, working as a delivery manager, writes to ISO 21502 with an agile cadence. The Proposal takes its delivery schedule from the approved plan.

What you get

A Markdown document titled Delivery Plan. The bridge adds the title block on top, the agent writes eight sections, and the bridge adds an Epic Register built from the plan's typed data, then the version history:

OrderSectionWritten by
1Title block: project, client, version, dateBridge
21. Summary: sprint count and length, the team assumed, client-visible milestones, the biggest risk to the dates, and what the velocity assumption rests onAgent
32. Epics: one per design component, with story count, relative size and the epics it depends onAgent
43. Sprint Plan: a Gantt chart, then a table of sprint, goal, epics and exit criteria, plus Definition of Ready and Definition of DoneAgent
54. Milestones: the sprint each lands in, its deliverables, how the client accepts it, including training and handoverAgent
65. Dependencies: build order, critical path, external dependencies with the sprint each is needed by, and a RACI table for the client's sideAgent
76. Team: the roles the plan assumes, their count and allocationAgent
87. Risks: risk, what it affects, likelihood, impact on the dates, mitigationAgent
98. AssumptionsAgent
10Epic Register: epics (id, title, sprint, depends on, requirements), milestones, and the team assumptionBridge
11Version HistoryBridge

The bridge requires these eight headings, at least one diagram, and a mermaid gantt chart among the diagrams. The skill asks the sprint plan to cover Sprint 0 (environments, CI/CD, Poly-X onboarding), the build sprints, hardening, UAT, release and cutover, and hypercare.

The Epic Register is owned by the bridge: editing the document keeps it as it is. It is written from the typed data the agent returns beside the document, and is left out when that data is empty.

Before you run it

  • The STS must be approved. Until it is, /plan is locked with "Approve System Test Spec to unlock this". The agent reads the approved SRS, TAD, SDS and STS as source documents.
  • The project state must hold the SDS and the STS. Otherwise the run stops with "Cannot write the Delivery Plan: sts artifact is missing from state.json. Run /sts first."
  • Run Tasks first if you can. When the build tickets exist, the plan is given a summary of each epic from them (title, dependencies, estimated story points, story count) and sizes the sprints from that. Without them it works from the number of implementation units in each design component. Tasks does not wait for the plan, so the order is your choice.

How it works

The step makes one sdlc-delivery-planner call. Its message holds the project start date (or none), every requirement's id, title and priority, each design component cut down to what scheduling needs (type, complexity, dependencies, units, assigned role), the number of test cases per component, the ticket summary when there is one, and the project's team roles and profiles.

The agent returns four things: the document, epics (each with the requirements it delivers, what it depends on and its sprint number), milestones (a sprint and what each demonstrates) and teamAssumption. The typed data restates the document, and is what the bridge checks and turns into the Epic Register.

Flow
  • Design components become epics to Planner assigns each epic a sprint
  • Ticket summary, or implementation unit counts to Planner assigns each epic a sprint
  • Planner assigns each epic a sprint to Epic scheduled before a dependency?
  • Epic scheduled before a dependency? to Note on the draft, Yes
  • Epic scheduled before a dependency? to Each milestone says what the client sees, No
  • Note on the draft to Each milestone says what the client sees
  • Each milestone says what the client sees to Gantt chart, every DC cited, no money or banned phrases?
  • Gantt chart, every DC cited, no money or banned phrases? to Notes on the draft, No
  • Gantt chart, every DC cited, no money or banned phrases? to Draft awaits your review, Yes
  • Notes on the draft to Draft awaits your review
  • Draft awaits your review to Bridge appends the Epic Register
  • Bridge appends the Epic Register to Approved plan feeds the Proposal

The checks

CheckWhat it enforces
Headings and diagramThe eight headings, one diagram at least, and a mermaid Gantt chart among the diagrams.
ComponentsEvery DC-NNN in the SDS is cited, and no DC-NNN that is not in the SDS appears.
Dependency orderNo epic sits in an earlier sprint than an epic it depends on.
TraceabilityEvery epic cites at least one requirement that exists in the SRS.
MilestonesEach milestone says in at least 12 characters what it demonstrates.
TeamA team assumption is stated.
No moneyNo amount such as $12,000, EUR 40 or 1,200 USD. Durations and story points pass.
Banned phrasesNone of TBD, N/A, to be determined, not available, placeholder, insert here, coming soon.
Typed dataepics, milestones and teamAssumption are present and every row has the fields it needs.

The plan has no blocking checks other than an empty document. Everything above is a note on the draft that the reviewer sees, except three that are hard: a missing required heading, an invented DC-NNN, and an empty document. A hard problem is kept on the draft as an open check, and Fix failed checks sends back only the sections it sits in and asks for the missing ones. The bridge makes no repair call by itself unless an operator allows more attempts. Draft notes never stop you approving, so read them.

The skill adds rules the bridge does not check: use teamProfiles names verbatim and never invent people, write a calendar date only when the input gives one (otherwise start on a Monday and say the dates are indicative), and recalibrate velocity after the first two sprints. The bridge checks only that a team assumption exists, not that it matches your roles.

The run panel shows: Checking project state, Planning the delivery, Writing the Markdown document.

Ids this step owns

The Delivery Plan creates no id prefix of its own. It cites ids from earlier steps and gives its own rows a short id the agent chooses:

IdMeaning
DC-NNNA design component from the SDS. Each one becomes an epic and is scheduled in a sprint.
REQ-…A requirement an epic delivers. Every epic cites at least one.
Epic and milestone idsFree-form, such as M1 for a milestone. They appear in the Epic Register and in dependsOn.

Reviewing it

The Delivery Plan is reviewed, and /proposal stays locked until it is approved. A project whose proposal was produced before this step existed counts its Delivery Plan as approved. Check that:

  • the sprint order follows the real build order: foundation first, nothing scheduled before what it needs;
  • the velocity basis is believable for the team in the Team section, and the team matches the roles your project has;
  • each milestone is something a client can see and accept, not "progress made";
  • the external dependencies (client data, third-party accounts, environments) have a sprint by which they are needed;
  • any dates exist in your scope or came from the project start date;
  • the notes on the draft, if any, are ones you accept.

Request changes sends the agent the draft and your change list. It returns only the sections and typed rows it changes. Name epics and sprints: "Move the reporting epic to sprint 5 and add the data migration rehearsal to hardening" works better than "the schedule is too tight".

When it fails

What you seeWhyWhat to do
/plan locked: "Approve System Test Spec to unlock this"The STS is not approved.Approve the STS.
"Cannot write the Delivery Plan: sts artifact is missing…"The project state has no STS.Run /sts first.
A note about a missing Gantt chartThe Sprint Plan has no mermaid gantt block.Request changes asking for one.
A note about a money figure, with the line numberAn amount appears in the text.Request changes: pricing is agreed separately.
A note about a dependency orderAn epic is in an earlier sprint than something it depends on.Request changes naming both epics.
A note about a design component not citedAn epic is missing for a component.Request changes naming it.
"The agent did not return a usable reply."No attempt produced readable output.Run it again.

Under the hood

  • The driver is bridge/src/services/planPipeline.service.ts, the skill sdlc-delivery-planner; the typed-data checks are in bridge/src/lib/documentQuality.ts.
  • The document is written to .sdlc/artifacts/plan-vN.md and registered as artifacts.plan. The draft and the agent's typed data are kept while it is under review, and approval removes them.
  • The gate sits in bridge/sdlc-engine/lib/sdlc/gate-rules.js. The checks and the repair call are described in Document checks and versioning.